Episode 26 — 120.82(A) Dwelling Unit Optional Calculation
We just entered Part IV — Optional Calculations.
Now we're getting into one of the most useful optional methods in Article 120:
But before you start adding up loads, there's a very important question:
Because this method isn't available for every dwelling.
To use this optional calculation method, the installation must meet all three of these conditions:
The optional method applies to a single dwelling unit.
The entire dwelling unit is supplied by one:
120/240-volt, 3-wire
or
208Y/120-volt, 3-wire
service or feeder.
That service or feeder must have a rating of at least:
Before using 120.82, ask:
YES / NO
YES / NO
YES / NO
120.82 may be available
You're looking at the standard calculation method instead.
Once you've passed the eligibility check, 120.82 breaks the optional calculation into three major load buckets:
General loads covered by 120.82(B).
↓
Covered by 120.82(C).
↓
Covered by 120.82(D).
Those three buckets are combined to determine the calculated load.
Remember our Part III finale?
The neutral calculation is still handled under:
So don't assume the optional method means you throw away everything you've already learned.
It doesn't erase the other applicable requirements.
Don't jump straight into the math.
First determine:
Does this dwelling qualify?
Then:
Calculate the three applicable load buckets.
Per 120.82(A), what is the minimum ampacity a dwelling's service or feeder must have to qualify for this optional method?
A) 60 amps
B) 100 amps
C) 200 amps
D) There is no minimum
👇 What's your answer?
The dwelling-unit optional calculation method in 120.82(A) requires the qualifying service or feeder to be rated at least 100 amperes.
But amperage alone isn't enough.
You also need the qualifying:
🏠 Single dwelling unit
⚡ One service or feeder
🔌 100A or greater
Continue exploring the JoshTheSparky Quick Hits library.
Test what you know with the JoshTheSparky Brain Busters.
Take the latest JoshTheSparky Question of the Week.
Go deeper into electrical thoughts, lessons, discoveries, and experiences in Sparky's Journal.
Follow the latest progress, discoveries, projects, and industry updates in Sparky Weekly.
Review the references and resources used throughout JoshTheSparky.com in the JoshTheSparky Sources library.
← Back to Article 120 Quick Hits
← Episode 25 — Welcome to Part IV
→ Episode 27 — 120.82(B) General Loads
Episode 26: Who Gets to Use This Shortcut?
Episode 27: General Loads
Episode 28: Heating & Air-Conditioning
Episode 29: EVSE Loads
Episode 30: Putting the Optional Method Together
This Quick Hit is an educational explanation based on the author's understanding of the NEC. It is not a substitute for the official NEC, applicable local amendments, manufacturer instructions, or the determination of the Authority Having Jurisdiction (AHJ).
Always verify the requirements applicable to your specific installation.
The National Electrical Code® and NEC® are registered trademarks of NFPA. JoshTheSparky.com is not affiliated with, sponsored by, or endorsed by NFPA.